PROCUREMENT: EU / DACH

Heavy Industrial
Steel Warehouses.

Procurement coordination for industrial steel halls and logistics buildings. Define S355 material requirements, crane loads and the EN 1090-2 execution and documentation scope with the selected fabricator.

Steel SelectionBy Design
NDT ScopePer EN 1090-2
Hall constructionHALLS-01

Portal frame

Transverse elevation

A pitched frame showing the relationship between columns, rafters and their connections.

  • 1 · Eaves connection and haunch
  • 2 · Ridge connection
  • 3 · Column base and anchors
  • L · Frame span; h · Eaves height

Concept illustration. Not for fabrication. Dimensions and connections require project-specific design.

Portal frame

A pitched frame showing the relationship between columns, rafters and their connections.

  • 1 · Eaves connection and haunch
  • 2 · Ridge connection
  • 3 · Column base and anchors
  • L · Frame span; h · Eaves height

Illustrative geometry. Dimensions, connections and member sizes require project-specific engineering.

Scope of Execution

From Micro-Plants to Mega-Centers.

From local warehouses to distribution centres, Steel-Hub coordinates the procurement brief. The selected fabricator confirms feasible spans, fabrication scope and delivery conditions against the approved design.

Mega Logistics Centers

Long-span warehouses require a defined support grid, loading-ramp interfaces and structural checks. Spans above 40 m must be assessed in the project design.

For E-Commerce & Retail

Heavy Production Facilities

Specify crane capacity, duty class and wheel loads, including heavy-duty applications. Columns and crane runways require project-specific dynamic and fatigue verification.

For Factories & Metallurgy

Cold Storage & Food

Coordinate insulated-panel supports, thermal-bridge details and rooftop solar loads within the structural and envelope design.

For Food Industry

Multi-story Structures

Steel galleries, industrial platforms and mezzanines can be included in the brief. Loads, fire requirements and fabrication interfaces are agreed per project.

Platforms & Mezzanines

Hangars, Agriculture & Custom Projects

Farms, riding arenas, silos and aviation hangars have different load and geometry requirements. The designer and selected fabricator confirm feasibility, tolerances and production scope before award.

Project-Specific Geometry

BIM Scope & Fabrication Data.

Where LOD 400 fabrication models are required, agree responsibility and deliverables with the selected fabricator. Model exchange from Tekla Structures and Autodesk Revit depends on the agreed workflow and compatible file formats.

  • ✓ Clash-detection scope for structure and installations
  • ✓ CNC file compatibility (.nc) confirmed with the fabricator
  • ✓ Bill of materials (BOM) checked against approved drawings
Crane runway1 · Rail and restraint. 2 · Beam web and flanges. 3 · Support connection. b · Flange width; h · Beam depth. Concept illustration. Not for fabrication. Dimensions and connections require project-specific design.hb123
Crane runway · Beam and support sections
  • 1 · Rail and restraint
  • 2 · Beam web and flanges
  • 3 · Support connection
  • b · Flange width; h · Beam depth
Concept illustration. Not for fabrication. Dimensions and connections require project-specific design.

Project Evidence for EU Procurement.

Request current certificates, traceability records and material documentation from the selected fabricator. Verify issuer, scope and validity against the project requirements before award; these are not Steel-Hub factory certifications.

EN 1090-2
EXC per specification
PER PROJECT
ISO 3834-2
Welding Quality Evidence
VERIFY SCOPE
NDT Scope
UT / MT as specified
INSPECTION PLAN
CE Mark
DoP where applicable
VERIFY APPLICABILITY
Logistics Command Center

Intermodal EU Connectivity.

Delivery planning should match component size, access and lifting requirements. Compare road, sea and air options with the carrier; routing, permits and timing are confirmed for each shipment.

Delivery planning

Example corridors
OriginĐakovoHR
  • MunichDE
    Road corridor
  • ViennaAT
    Road corridor
  • Koper / RijekaSI / HR
    Port transfer

Schematic connections, not a geographic map. Route, permits and delivery windows are agreed for each project.

Airports (Air Freight)

Subject to Booking

Urgent service packages and inspection visits may use Osijek or Zagreb airports. Flight availability, cargo acceptance, onward transport and inspection access must be agreed before travel or dispatch.

Engineering Knowledge Base.

Technical points for procurement and design review.

Knowledge Base

Related procurement guides

EN 1090 EXC3: supplier certificate verification checklist→